SUBJECT:
title
Approval of a resolution authorizing the President & CEO, or his designee, to finalize and execute a contract with Modern Railway Systems, Inc., for the construction of the Lakeline to Leander Double Track Project, plus optional McKalla special track components for a total not to exceed amount of $8,301,404, which includes a 20% contingency.
end
FISCAL IMPACT:
Funding for this action is available in the FY2022 Capital Budget
STRATEGIC PLAN:
Strategic Goal Alignment:
☒ 1. Internal/External Customer Service Excellence ☐ 2. Stakeholder Engagement
☐ 3. Financial and Environmental Sustainability ☐ 4. Staff Development ☐ 5. Agency Growth Management
Strategic Objectives:
☐ 1.1 Safety & Risk ☒1.2 Continuous improvement ☐ 1.3 Dynamic Change
☐1.4 Culture of Innovation ☐2.1 Be an Employer of Choice ☐2.2 Organization Development
☐2.3 Organization Culture ☒3.1 Resource optimization ☒3.2 Safety Culture
☐3.3 Environmental Leadership ☐4.1 Educate & Call to Action ☐4.2 Build Partnerships
☒4.3 Value of Transit ☐4.4 Project Connect
EXPLANATION OF STRATEGIC ALIGNMENT: Currently, there is a single main track between the Lakeline and Leander Stations. There is a need for a double track midway between the Lakeline and Leander Stations to establish a meet point for passing trains in order to support plans for improved service frequency and reliability.
BUSINESS CASE: To support Capital Metro’s goal of continuous improvement of the customer experience, a segment of double track is necessary between the Leander and Lakeline stations. The funding for this project is included in the FY 2022 capital budget and five year capital improvement plan
COMMITTEE RECOMMENDATION: This item was presented and recommended for approval by the Operations, Planning and Safety Committee on August 18, 2021
EXECUTIVE SUMMARY: In 2020, Capital Metro began working on feasibility options for double tracking sections of the railroad in order to provide improved frequency in full compliance with the Board adopted safety standards and reliability of transit service. After evaluating several options, a location between the Lakeline and Leander Stations (Park Street and Discovery Blvd.) was selected as the priority for design and construction of a double track section. This segment of double track will support the agency’s future service plans, including improved service frequency and reliability
The contractor will construct the additional track and associated retaining wall, replace a 15-foot bridge with a precast concrete culvert, encase the base water line under the tracks, add wayside signalization and make necessary modifications to the Positive Train Control (PTC) system. This contract also includes the option for providing a rail crossover and turnout for the McKalla rail station project.
DBE/SBE PARTICIPATION:
The SBE goal is 19.70%. The prime contractor will meet 23.9% utilizing the following SBE subcontractors:
DBE Subcontractors |
Race/Gender |
Services/Products |
DBE Responsive |
McAllen Signal and Boring McAllen, TX |
Hispanic / Female |
Install Signal System |
6% |
HAFCO Austin, TX |
Hispanic/ Male |
Supply and Install Track |
15% |
JC Communications Leander, TX |
Caucasian/ Female |
Supply, Install, Splice, Conduit, and Fiber |
.9% |
Environmental Safety Services Austin, TX |
Hispanic/ Male |
Erosion Controls |
1.2% |
Avery’s Lawn Care & Landscaping Round Rock, TX |
Black/ Male |
Supply and install erosion controls |
.8% |
|
23.9% |
PROCUREMENT: On May 6, 2021, a Request for Proposal was issued and formally advertised. By the closing date of June 14, 2021, four (4) proposals were received. The proposals were rated based on the following evaluation factors:
1.) The offeror’s demonstrated, relevant work experience and capabilities of the firm and of the proposed project personnel on projects of a similar size and complexity. (30%)
2.) Experience in design of Signal systems and PTC modifications and installation & testing. (25%)
3.) Demonstrated understanding of the requirements in the Technical Specifications, Plans, and the Scope of Work as described in Exhibit F. (25%)
4.) Offeror’s Demonstration of financial capability is appropriate to the size and scope of the project. (20%).
The proposal from Modern Railway Systems was ranked highest, all factors considered. The contract is a fixed price contract. The period of performance is for 365 calendar days from Notice to Proceed.
RESPONSIBLE DEPARTMENT: Capital Projects
body
RESOLUTION
OF THE
CAPITAL METROPOLITAN TRANSPORTATION AUTHORITY
BOARD OF DIRECTORS
STATE OF TEXAS
COUNTY OF TRAVIS
AI-2021-136
WHEREAS, the Capital Metropolitan Transportation Authority Board of Directors and Capital Metro management endeavor to provide the best customer service experience and to better serve Central Texas residents; and
WHEREAS, the Capital Metropolitan Transportation Authority Board of Directors and Capital Metro management recognize the need for a segment of double track for the MetroRail Red Line between Park Street and Discovery Blvd.
NOW, THEREFORE, BE IT RESOLVED by the Capital Metropolitan Transportation Authority Board of Directors that the President & CEO, or his designee, is authorized to finalize and execute a contract with Modern Railway Systems, Inc., for the construction of the Lakeline to Leander Double Track Project, plus optional McKalla special track components for a total not to exceed amount of $8,301,404, which includes a 20% contingency
____________________ Date: ____________________
Secretary of the Board
Eric Stratton